SY0-701 practice question on Risk management, 2026-11-14

Archived question for 2026-11-14. Domain: Security program management and oversight. Objective 5.2: Risk management. Original SecLern question, written for practice.

A city bus operator's finance team is reviewing outages of its onboard payment terminals. Each outage costs about $4,000 in technician overtime and $2,500 in uncollected fares, and outages have occurred about once every three months for several years. Which annualized loss expectancy (ALE) should the team record for this risk?

Show the explanation

One outage costs $4,000 + $2,500 = $6,500, which is the single loss expectancy (SLE). Once every three months is four outages a year, so the annualized rate of occurrence (ARO) is 4. ALE is the total expected loss over a year: $6,500 x 4 = $26,000.

Each option

  • A. $1,625 divides the cost of one outage by four, which treats the rate as one outage every four years. It would be right if outages happened once in four years.
  • B. $6,500 is the cost of a single outage, the SLE. It covers one outage, not a whole year. It would be right if the question asked for the SLE, or if only one outage a year were expected.
  • C. $16,000 is four outages at $4,000 each, which counts the overtime and leaves out the uncollected fares. It would be right if an outage cost nothing in fares.
  • D (correct). Correct: $6,500 per outage x 4 outages a year = $26,000.

What this question tests

It maps to SY0-701 objective 5.2, Risk management: Explain elements of the risk management process. Related ideas: ale, sle, aro, quantitative risk.

The published topics under this objective, so you can check what you have covered:

  • Risk identification
  • Risk assessment > Ad hoc
  • Risk assessment > Recurring
  • Risk assessment > One-time
  • Risk assessment > Continuous
  • Risk analysis > Qualitative
  • Risk analysis > Quantitative
  • Risk analysis > Single loss expectancy (SLE)
  • Risk analysis > Annualized loss expectancy (ALE)
  • Risk analysis > Annualized rate of occurrence (ARO)
  • Risk analysis > Probability
  • Risk analysis > Likelihood