CISM practice question on Information security, 2026-11-08

Archived question for 2026-11-08. Domain: Information Security Governance. Objective D1.2: Information security. Original SecLern question, written for practice.

Funds are available for one of two projects that cost the same. Project A removes a risk rated High on a minor internal system: a loss of 50,000 dollars is expected about once a year. Project B removes a risk rated Medium on the main revenue system: a 10 percent yearly chance of a 2 million dollar loss. Which should the manager recommend?

Show the explanation

Funding follows the larger expected business loss: B is 200,000 dollars a year against 50,000 for A, whatever the rating label says.

Each option

  • A (correct). Correct: Expected annual loss is 10 percent of 2,000,000, or 200,000, which is four times the 50,000 that Project A removes.
  • B. The rating label ignores the size of the loss. It would be right if the expected annual losses were similar.
  • C. Ease of protection is not the stated priority. It would be right if both projects removed similar expected loss.
  • D. Splitting may leave both unfinished. It would be right if each could be delivered in useful part.

What this question tests

It maps to CISM objective D1.2, Information security: Information security strategy Related ideas: planning, prioritization, impact.

The published topics under this objective, so you can check what you have covered:

  • Strategy development
  • Governance frameworks
  • Standards
  • Strategic planning including budgets
  • Resources
  • Business case