N10-009 practice question on Disaster recovery, 2026-11-09

Archived question for 2026-11-09. Domain: Network Operations. Objective 3.3: Disaster recovery. Original SecLern question, written for practice.

A payment processor may be offline for no more than a few minutes after losing its primary data center, and it cannot lose recent transactions. Which kind of alternate site fits?

Show the explanation

Minutes of downtime and no lost transactions need a fully operational site with current data. Partial equipment, bare space or weekly backups all recover too slowly or lose too much.

Each option

  • A. Completing setup and restoring data takes hours. It would be right for a target of about a day.
  • B (correct). Correct: A hot site is fully operational with hardware and software, so it can take over within minutes.
  • C. Buying and installing equipment takes days. It would be right for a low-cost plan with a long target.
  • D. Weekly backups could lose days of data. It would be right where days of loss are acceptable.

What this question tests

It maps to N10-009 objective 3.3, Disaster recovery: Explain disaster recovery (DR) concepts. Related ideas: hot site.

The published topics under this objective, so you can check what you have covered:

  • DR metrics > Recovery point objective (RPO)
  • DR metrics > Recovery time objective (RTO)
  • DR metrics > Mean time to repair (MTTR)
  • DR metrics > Mean time between failures (MTBF)
  • DR sites > Cold site
  • DR sites > Warm site
  • DR sites > Hot site
  • High-availability approaches > Active-active
  • High-availability approaches > Active-passive
  • Testing > Tabletop exercises
  • Testing > Validation tests

More from the archive

Start a daily session

Several questions at a time, aimed at your gaps.