ISACA CISM practice question 6: Risk management

After treating a risk, the remaining level is still above the organization's tolerance. What is the most appropriate next step?

The options

  • A. Lower the tolerance level so the risk fits.
  • B. Wait for an incident to prove the risk is real.
  • C. Remove the risk from the register.
  • D. Report the residual risk to the risk owner for a decision on further treatment or formal acceptance.

Answer and why

The correct answer is D: Report the residual risk to the risk owner for a decision on further treatment or formal acceptance.

A. Changing tolerance to fit the result avoids the decision instead of making it.

B. Waiting accepts the risk by default without a decision.

C. Deleting it hides a known risk.

D. Risk above tolerance needs a documented decision by the accountable owner.

What Risk management tests

Information security risk management covers assessment, treatment, ownership and reporting. The risk belongs to the business owner, so look for who decides on treatment and what information they need to decide.

Information security risk management is 20% of the CISM exam. The exam has 150 questions in 240 minutes, so this question is a slice of the real mix, not a prediction of your result.

Try these next

Each one is a free question from the same practice test, with the answer and the reason for every option on its own page.

Keep going

This is question 6 of 15 in the free ISACA CISM practice test. If you missed it, say why in one sentence before you read on: the reason is what transfers to a differently worded question.